Retention money and advance payment recovery: how to calculate them

QS Mentor Knowledge Centre · Payment applications & certification · Updated 2026-11-10 · 5 min read

Both deductions are simple percentages, and both are calculated wrong surprisingly often. Read the rates, limits and mechanisms from the contract each time: they differ between projects.

Retention

Retention is calculated on the cumulative eligible valuation (the work the contract says retention applies to), at the stated rate, up to the contractual limit. The amount deducted in the current certificate is the difference between cumulative retention and retention previously deducted. Release (often half at completion and the rest at the end of the defects period) follows the contract.

Example: contract sum AED 10,000,000; retention 10% up to 5% of the contract sum (AED 500,000).

Advance payment recovery

An advance payment (often 10–20% of the contract sum, against a bank guarantee) is recovered through the agreed contractual mechanism: commonly a percentage of each valuation, sometimes starting only after a threshold, as in FIDIC Sub-Clause 14.2. As with retention, work cumulatively: cumulative recovery to date, less recovery previously deducted.

Example: advance AED 1,000,000 recovered at 20% of each cumulative gross valuation. At a cumulative gross of 3,000,000 the cumulative recovery is 600,000; at 5,000,000 it reaches the full 1,000,000 and stops.

Common mistakes

Every QS Mentor valuation checks retention and advance recovery against the subcontract terms. Try one free.