Joint measurement (JMS) and WIRs: quantity surveying site measurement records

QS Mentor Knowledge Centre · Measurement & BOQ · Updated 2026-11-10 · 5 min read

A payment is only as good as the records behind it. Two records do most of the work.

The joint measurement sheet

A JMS records quantities measured jointly on site by the contractor and the subcontractor up to a cut-off date. It should be jointly agreed and supported by reliable measurement records, following the contract's measurement procedure; on most projects both parties sign it. It is normally cumulative: previous total, this period, and the agreed cumulative quantity. Where measuring on site is not practical, the parties mark the work on a dimensioned drawing and the QS takes the quantity off it.

The work inspection request

A WIR asks the consultant or the contractor's QA/QC team to inspect an element before it is covered up or valued. Many Gulf projects code the response A (approved), B (approved with comments) or C (rejected, revise and re-inspect). Inspection codes and their meanings depend on the project's approved inspection procedure and QA/QC documentation, so check yours.

How a QS uses them together

  1. Check the claimed cumulative quantity against the joint measurement.
  2. Check that the work in the period is supported by the inspection records the contract and the inspection procedure require, dated before the cut-off.
  3. Leave work done or inspected after the cut-off for the next valuation.
  4. Where the JMS points to a take-off drawing, measure it from the figured dimensions.

QS Mentor gives you scanned JMSs, WIR logs, take-off drawings and pour registers to work from. See it free.