Joint measurement (JMS) and WIRs: quantity surveying site measurement records
A payment is only as good as the records behind it. Two records do most of the work.
The joint measurement sheet
A JMS records quantities measured jointly on site by the contractor and the subcontractor up to a cut-off date. It should be jointly agreed and supported by reliable measurement records, following the contract's measurement procedure; on most projects both parties sign it. It is normally cumulative: previous total, this period, and the agreed cumulative quantity. Where measuring on site is not practical, the parties mark the work on a dimensioned drawing and the QS takes the quantity off it.
The work inspection request
A WIR asks the consultant or the contractor's QA/QC team to inspect an element before it is covered up or valued. Many Gulf projects code the response A (approved), B (approved with comments) or C (rejected, revise and re-inspect). Inspection codes and their meanings depend on the project's approved inspection procedure and QA/QC documentation, so check yours.
How a QS uses them together
- Check the claimed cumulative quantity against the joint measurement.
- Check that the work in the period is supported by the inspection records the contract and the inspection procedure require, dated before the cut-off.
- Leave work done or inspected after the cut-off for the next valuation.
- Where the JMS points to a take-off drawing, measure it from the figured dimensions.
QS Mentor gives you scanned JMSs, WIR logs, take-off drawings and pour registers to work from. See it free.