How to assess a subcontractor payment application (IPA), step by step

QS Mentor Knowledge Centre · Payment applications & certification · Updated 2026-11-10 · 7 min read

An interim payment application (IPA) is the subcontractor's claim for the work done to a cut-off date. Your job as the main contractor's QS is to value what the records and the subcontract support, no more and no less, and to explain every adjustment. Here is the order experienced QSs work in.

1. Start with the subcontract, not the application

Before you open the claim, note the terms that change the numbers: the retention rate and its limit, the advance payment and how it is recovered, the treatment of materials on site, the payment and assessment periods, the inspection and quality requirements, and whether the subcontract is re-measured or lump sum.

2. Check the measured work line by line

For each BOQ item, compare the cumulative quantity claimed with the joint measurement agreed at the cut-off. If no joint measurement covers the item, measure it yourself from the drawings to the stated method of measurement. Then recompute the amount: quantity × contract rate. Common problems are quantities above what was measured, work after the cut-off, rates that differ from the BOQ, and simple arithmetic errors.

3. Confirm the inspection records support the work

Check the subcontract's payment and quality requirements and confirm that the relevant inspection records support the claimed work. On many Gulf projects that means a work inspection request (WIR) for each element with new work in the period, inspected before the cut-off under the project's inspection procedure. Where work has been rejected, or is still awaiting inspection, find out what the subcontract says before you value it.

4. Variations: check the basis before you value

Do not automatically certify an uninstructed variation, and do not automatically reject it either. Check whether there is a contractual entitlement: a valid instruction, a deemed instruction, or another basis for payment under the subcontract. On a FIDIC-based main contract the Engineer instructs under Sub-Clause 3.3 (1999) or 3.5 (2017), and the main contractor passes instructions down under the subcontract. Then compare with the VO register: pay agreed variations at the agreed value, and where a value is not yet agreed many contractors include a fair interim assessment and say so.

5. Materials on site

Materials delivered but not yet built in are included only if the subcontract allows it, on its stated basis (often a percentage of the invoiced value), and only for materials that are on site, properly stored and not already counted in measured work. Check delivery notes and the material inspection request (MIR).

6. Deductions and the amount due

From the cumulative gross valuation, deduct cumulative retention (at the rate, up to its limit), cumulative advance recovery, any agreed contra charges, then the amount previously certified. The result is the amount due this period, before VAT.

7. Prepare the certificate with reasons

Depending on the subcontract procedure, the contractor's QS prepares the interim payment certificate (IPC) or recommends it for approval. It states what is certified and why each line differs from the claim. A short covering letter that names the record behind each adjustment ("item 2.02 certified at 833 m³ per JMS-01") prevents most disputes.

Standard form or your contract? References here are to the published FIDIC Red Book (1999 and 2017). Particular Conditions, the subcontract and the governing law often change them: always read your own contract first.

Practise it. On QS Mentor your first task is exactly this: a real-format IPA with planted errors, a JMS, WIRs and a VO register, marked against the subcontract. Try it free.

Questions

What is the difference between an IPA and an IPC?

The IPA (interim payment application) is what the subcontractor claims. The IPC (interim payment certificate) is what the contractor’s QS certifies or recommends as due after checking the claim against the subcontract and the records.

What records do I need to assess an IPA?

The subcontract and its BOQ, the joint measurement at the cut-off, the inspection records, the instructions and VO register, and the previous certificate. For materials on site, add delivery notes and material inspection records.