IPA vs IPC: interim payment application and certificate explained

QS Mentor Knowledge Centre · Payment applications & certification · Updated 2026-11-10 · 5 min read

In Gulf construction the two terms appear on every project. They are two sides of the same monthly payment, and they work slightly differently under a subcontract and under the main contract.

Under a subcontract

Under a FIDIC main contract

Many UAE contractors call their Statement an "IPA" too, which is why graduates hear the terms used loosely. Check which document you are holding and whose procedure applies.

How the figures flow

Worked example

Gross valuation AED 2,000,000. Retention 10%: AED 200,000. Advance recovery 10%: AED 200,000. Net cumulative AED 1,600,000. Previously certified AED 900,000. Amount due AED 700,000 before VAT. Working cumulatively corrects last month's errors automatically.

Standard form or your contract? References here are to the published FIDIC Red Book (1999 and 2017). Particular Conditions, the subcontract and the governing law often change them: always read your own contract first.