POMI vs NRM2 vs CESMM4: quantity surveying measurement standards compared
A quantity is only correct under a stated method of measurement. The contract names one, and the preambles to the BOQ say how it applies on that project. These are the three standards you are most likely to meet.
POMI
RICS Principles of Measurement (International). Widely used for building and fit-out work in the Middle East. It sets out general principles and work sections and leaves much of the detail to the project documents, so on a POMI job the preambles carry a lot of weight.
NRM2
RICS New Rules of Measurement, detailed measurement for building works. The UK standard, also used internationally, with detailed work sections, units and rules for what each item includes.
CESMM4
The ICE Civil Engineering Standard Method of Measurement, fourth edition. Used mostly for infrastructure and civil engineering: roads, bridges, metro and rail, utilities, drainage, earthworks, piling and marine works. Work is classified into classes A to Z with a coding system, and items are often measured net with method-related charges separated out.
The preambles: where the standard meets the project
The preambles (sometimes called the measurement preambles or the preliminaries to the BOQ) state which standard applies and then adapt it: what each item is deemed to include, deduction thresholds for openings, units, rounding, items measured as lump sums, and any departures from the standard. When a preamble and the standard differ, the preamble usually governs for that contract. Read them before you measure, and quote them when you defend a quantity.
How to tell which applies
- Read the measurement clause and the preambles.
- Note every amendment to the standard.
- Measure to that method only. Mixing methods within one bill is a common source of disputes.
On QS Mentor the building and fit-out projects are measured to POMI principles and the metro to CESMM4 principles, each as amended by its own preambles.
Practise measuring to the stated method, with dimension sheets and take-off drawings.