Extension of time and claims under FIDIC 2017: the 28-day notice and 84-day claim

QS Mentor Knowledge Centre · Variations, claims & FIDIC · Updated 2026-11-10 · 7 min read

Claims are lost on dates more often than on merit. Know the procedure of the form you are working under, and check the Particular Conditions, which often change it. This is a summary: read the full sub-clauses before relying on it.

FIDIC 2017: the steps in Sub-Clause 20.2

  1. Notice of Claim (20.2.1). The Contractor gives notice as soon as practicable and not later than 28 days after becoming aware, or when it should have become aware, of the event or circumstance. If it does not, the Contractor loses entitlement to the additional time or payment for that event, subject to what follows.
  2. The Engineer's initial response (20.2.2). If the Engineer considers the Notice late, the Engineer must say so, with reasons, within 14 days of receiving it. If the Engineer does not, the Notice is treated as valid. A Contractor who disagrees, or who considers that circumstances justify the late notice, sets that out in its fully detailed Claim.
  3. Contemporary records (20.2.3). Keep them from the start; the Engineer may inspect them.
  4. Fully detailed Claim (20.2.4). Within 84 days of becoming aware (or another period the Engineer agrees), including a description of the event, the contractual or other legal basis, the records, and the time and money claimed. If the statement of the contractual or legal basis is not submitted in time, the Notice of Claim lapses; the Engineer is again expected to give notice of that within 14 days, failing which the Notice is treated as valid, and the Contractor can again argue that the late submission was justified.
  5. Agreement or determination (20.2.5 with 3.7). The Engineer proceeds to agree or determine the claim. Where lateness is disputed, that review can consider whether the late submission is justified, taking account of matters such as the Employer's prejudice and prior knowledge.
  6. Continuing events (20.2.6). The fully detailed Claim is interim, updated monthly, with a final claim after the event ends.

So neither extreme is right: a late claim is not automatically lost, and it is not automatically excused. The outcome depends on the notices given, the Engineer's responses, and the determination.

FIDIC 1999 (Sub-Clause 20.1)

Notice within 28 days of awareness; a fully detailed claim within 42 days, or another period proposed by the Contractor and approved by the Engineer; the Engineer responds within 42 days. If notice is not given within 28 days, the extension of time and additional payment are not available for that event.

What the QS tracks

Standard form or your contract? References here are to the published FIDIC Red Book (1999 and 2017). Particular Conditions, the subcontract and the governing law often change them: always read your own contract first.

QS Mentor includes late-notice claims and EOT assessments on a live metro project. Try a free task.

More guides

General guidance for learning. Contract references are to the published FIDIC forms; your project's particular conditions and the governing law decide. This is not legal advice.